The Apapa-Wharf Road reconstruction in Lagos State has achieved only 10 per cent completion, an official of the Federal Ministry of Power, Works and Housing has said.
An FMPWH engineer supervising the project, Mrs. Olukorede Keisha, said on Tuesday at the project site that presence of gas pipes and other public utilities in the road’s Right of Way delayed the project execution.
The engineer spoke in an interview.
She said the contractors handling the project had, however, resolved the problem.
Keisha said 200 metres of concrete road and 230 metres of drains had been constructed on section one of the project.