Costa Concordia Ready for 10-Mile Tow

by Joshua
May 8, 2015
in Uncategorized

The Costa Concordia wreck is ready to be moved to a new dock about 10 miles away from its current location, where the ship will continue to be dismantled.
Since arriving in Genoa, Italy in July 2014, the Costa Concordia has been berthed at Prà Voltri Port where the first phase of the dismantling and scrapping project has taken place.

The Costa Concordia wreck is ready to be moved to a new dock about 10 miles away from its current location, where the ship will continue to be dismantled.
Since arriving in Genoa, Italy in July 2014, the Costa Concordia has been berthed at Prà Voltri Port where the first phase of the dismantling and scrapping project has taken place.
 Phase 1 of the project involved the removal of over 5,700 tons of materials from the ship – such as furniture and internal structures – in order to reach the draft required for the transfer from the breakwater at Prà Voltri to the Port of Genoa “Molo Ex Superbacino” area, about 10 miles away, where the next phases of the project will be carried out.
The Ship Recycling Consortium, which is made up of the Italian company Saipem (51%) and San Giorgia del Porto (49%), says it is now awaiting formal authorization for the transfer.
Weather and sea conditions are obviously a key factor that will determine exactly when the tow will commence, however the Consortium has said that they are looking for the best weather window starting next week.
 The tow is expected to take about 24 hours and will include exit maneuvers from the Prà Voltri breakwater, navigation (expected to last about 11 hours), and the entrance maneuvers in the ex Superbacino dock area of the Genoa Port.
The entire dismantling project is made up of four individual phases. Phase two kicks off with the transfer, followed by the dismantling of structures from decks 14 to 2. After that, Phase 3 involves preparing the wreck for its transfer to dry dock, located in the same harbor, where the ship will eventually be fully dismantled and recycled during Phase 4.
 The main objective of Phase 3 will be to create bouyancy which will allow for the removal of the 30 sponsons currently keeping the wreck afloat. The entire dismantling project is expected to take a total of about 22 months and will involve between 100 and 250 personnel working at any given time.
 


Related Posts

CMSN Inducts 40 Professionals, Boosts Local Capacity in Marine Surveying

CMSN Inducts 40 Professionals, Boosts Local Capacity in Marine Surveying

April 6, 2026

NPA Targets N1.489tn Revenue For 2026

March 31, 2026

Police Intercept Teen In Alleged Lagos Airport Stowaway Attempt

March 31, 2026
MSC

WEEKLY GLOBAL MARINE INCIDENTS

March 23, 2026

Discussion about this post

Latest News

Maritime Sector Faces Priority Alignment Challenges – Centre

Maritime Sector Faces Priority Alignment Challenges – Centre

April 17, 2026

NSC Pushes Fast-Track Clearance of Power Project Cargo at Ports

Oyetola Commissions NIMASA–UNILAG Institute of Maritime Studies Building, Reaffirms Commitment to Blue Economy Growth

Vessels Expected At Lagos Ports As At 17th April, 2026

Reforms Drive Maritime Turnaround, Position Nigeria for Blue Economy Leadership — Dantsoho

Tariff Hike: Freight Forwarders Demand Policy Review, Stronger Local Content Protection

Customs Boss Pledges Multimedia Centre, Radio Station For NIJ

MWUN, Maritime Unions Threaten Action Against Temile Over Workers’ Unionisation Dispute

NCS Seizes Smuggled Donkey Skin, PMS Worth N98.3 Million In Adamawa

Vessels Expected At Lagos Ports As At 16th April, 2026

NIJ Honours Customs CG Adeniyi with Fellowship, Announces Landmark Multimedia Centre Donation

NIMASA DG Commends NSDP Graduates As 34 Beneficiaries Obtain CoC

kindly like our Facebook page

Health

Sleep Deprivation Root Cause Of Many Disease – Says Physician
Health

Health Benefits Of Consuming Garden Egg

March 23, 2026

A great source of dietary fibre, minerals and vitamins, garden eggs are a welcomed addition to every meal. This fruit...

Sleep Deprivation Root Cause Of Many Disease – Says Physician

Sleep Deprivation Root Cause Of Many Disease – Says Physician

March 23, 2026
Report Finds Hypertension Affects Up To 40% Of Nigerian Adults In 2025

Stress Management: Psychiatrist Identifies Effective Coping Mechanisms

March 16, 2026
Report Finds Hypertension Affects Up To 40% Of Nigerian Adults In 2025

Report Finds Hypertension Affects Up To 40% Of Nigerian Adults In 2025

March 16, 2026
Lemons Are Among Fruits That Have The Highest Healing Powers Of Diseases On Earth

Lemons Are Among Fruits That Have The Highest Healing Powers Of Diseases On Earth

March 9, 2026
Nigeria Reports Higher Lassa Fever Death Rate

Nigeria Reports Higher Lassa Fever Death Rate

March 9, 2026
The Big Question: Can Diabetes Be Reversed?

Some Early Warning Signs of Diabetes That You Don’t Know, But Should

March 2, 2026
Why Your Favourite Seasoning Cubes May Be Hurting Your Kidneys

Why Your Favourite Seasoning Cubes May Be Hurting Your Kidneys

February 23, 2026
SHOCKING: FIIRO Links High Rates of Organ Failure, Cardiovascular Diseases in Nigeria to Local Grinding Machines

SHOCKING: FIIRO Links High Rates of Organ Failure, Cardiovascular Diseases in Nigeria to Local Grinding Machines

February 23, 2026
MONDAY INTERVIEW: Oyebamiji Did Not See The Media As Adversaries, But As Partners In Development”—Minister Oyetola

DANGER: 11% Of Nigerians Have Kidney Disease – Experts

February 16, 2026

© 2021 Shippingposition

Navigate Site

  • Home
  • About Us
  • Contact us
  • Privacy Policy
  • Editorial Policy
  • Sitemap
  • Terms

Follow Us

No Result
View All Result
  • News
  • Coast To Coast
  • Oil and Gas
  • Maritime Education
  • The Terminals
  • Maritime safety

© 2021 Shippingposition