China Harbour Engineering Company (CHEC) and Lekki Port Company have completed the formalities of signing a contract in which CHEC will commence building Nigeria’s new deepwater port at Lagos.
CHEC’s vice president, Lin Yichong, attended the meeting to sign the contract.
China Harbour Engineering Company (CHEC) and Lekki Port Company have completed the formalities of signing a contract in which CHEC will commence building Nigeria’s new deepwater port at Lagos.
CHEC’s vice president, Lin Yichong, attended the meeting to sign the contract.
The first phase of the new port will cost approximately US $679 million and will take 42 months to complete. This covers construction of the 2.2km long breakwater, a 6km long navigation channel, a multi-purpose quay, another quay with three berths to accommodate container ships with a maximum capacity of 8,000-TEUs, berths for workboats, storage yards, and a retaining wall.
Upon completion, the project will see Nigeria having one of the largest deepwater ports in West Africa.